  • Transporters underneath the steel truss bridge span
  • Transporters underneath the steel truss bridge span
  • Transferring the weight of the bridge to longer beams
  • Pin bearings in the process of being installed at the eastern abutment
  • Movement of the bridge between the two northern lifting towers
  • Moving the bridge between the two northern lifting towers
  • Looking west to the marina from Grand Avenue Park at the painted steel truss bridge span in West Marine View Drive.
  • Construction of falsework above the pipelines
  • Construction of falsework above the pipelines
  • Looking at the end of the painted steel truss bridge span
  • Painting of portions of the steel truss bridge span
  • Connecting steel members
  • Heavy steel members placement
  • Final pavement on W Marine View Drive
  • Grand Ave Park Bridge looking south
  • Grand Ave Park Bridge looking north
  • Complete assembly of Grand Ave Park Bridge
  • Weathering steel
  • Grand Ave Park Bridge looking north
  • Assembly of the bridge in WMVD mid-April 2019
  • Assembly of truss bridge in WMVD mid-April 2019 (future north side of bridge)
  • Gusset plate with bolt inspection marks
  • GAPB construction
  • Assembly of the truss bridge and installation of steel utility pipes in lower level
  • Assembly of truss bridge in WMVD mid-April 2019 (future south side of bridge)
  • Night Bridge View
  • Night Aerial Elevation
  • Aerial Elevation
  • GAPB Aerial
  • Wiring installation for elevator controls
  • Utility shaft roof
  • Installation of rails and equipment for elevator
  • Installation of rails and equipment for elevator
  • Elevator machine and installation 1
  • Elevator machine and installation 2
  • Turnaround at west tower parking lot
  • Installation of roof for utility tower
  • Sandblasting patterns 2
  • Trial bridge assembly
  • Sandblasting patterns
  • WMVD paving
  • Utilities pipes at roof level
  • Utility shaft access door
  • Tower sandblasting
  • Hydroseeding
  • Forms and rebar for upper external concrete pour
  • Concrete pour for internal elevator control room
  • Completion of slope stabilization east abutment
  • Template for sandblasting
  • Preparing tower for sandblasting
  • Elevator shaft forming and rebar
  • East abutment concrete pour
  • Steel bridge members in Vancouver
  • Pipeline installation
  • GAPB soil stabilization 1
  • GAPB soil stabilization 2
  • GAPB hillside pipelines 1
  • GAPB Hillside Pipelines 2
  • GAPB elevator shaft 1
  • GAPB elevator shaft 2
  • Aerial
  • Aerial Elevation
  • Lifting Large Diameter Pipelines into Trench Box
  • Excavation at North End of Grand Avenue Park
  • Night Aerial Elevation
  • Aerial Elevation
  • Night Bridge View
  • Large Diameter Utility Pipes Installed to Edge of Slope
  • Large Diameter Pipes in Hillside with Train
  • Hillside Soil Stabilization Installation
  • View of Tower Construction from Park Looking West
  • Lifting Large Diameter Pipelines into Trench Box
  • Large Diameter Utility Pipes on Park Side
  • Exterior Tower Wall Forms and Rebar
  • Exterior Tower Wall Construction
  • Excavation at North End of Grand Avenue Park
  • Exterior Walls as Forms are Being Removed