News Flash

Posted on: September 13, 2019

Rucker Renewal project update 9-13-19

Rucker project logo

THIS WEEK

Hoyt

The sidewalks and curb are almost finished on the east side.

Rucker

The contractor installed storm drain on Hewitt and demolished, graded the roadway from California to Hewitt and laid electrical and irrigation. Phase 2 waterline work included ...

Read on...

Additional Info... Rucker Renewal Project Updates
Posted on: September 6, 2019

Rucker Renewal project update 9-6-19

Rucker project logo

THIS WEEK

Hoyt

The contractor began constructing sidewalks, continued pouring curbs and installed traffic detecting loops. 

Rucker

The contractor installed storm drain on Hewitt and demolished and graded the roadway from California to Hewitt. Phase 2...

Read on...

Rucker Renewal Project Updates
Posted on: August 30, 2019

Rucker Renewal project update 8-30-19

Rucker project logo

*A new map showing all three stages of construction, the timing and sequencing for each stage and a listing of affected businesses is now available on the project webpage.

THIS WEEK

Hoyt

The contractor began pouring curbs and continued directional boring and...

Read on...

Rucker Renewal Project Updates
Posted on: August 23, 2019

Rucker Renewal project update 8-23-19

Rucker project logo

See this and other images of historical finds from the Rucker Renewal project in the photo gallery.

THIS WEEK

Hoyt

The contractor completed demolition of the east sidewalk and began directional boring and irrigation work in support of creating a new sidewalk...

Read on...

Rucker Renewal Project Updates
Posted on: August 16, 2019

Rucker Renewal project update 8-16-19

Rucker project logo

*Note: Extended closure of Hewitt/Rucker intersection coming Monday, August 19. See below for more information.

THIS WEEK

Hoyt

The contractor completed concrete paving and construction of a crosswalk mid-block, near the south end of Imagine Children&rsqu...

Read on...

Rucker Renewal Project Updates
Posted on: July 22, 2019

Rucker Renewal project update 8-9-19

Rucker project logo

THIS WEEK

Hoyt

The contractor continued concrete paving and work to establish a crosswalk mid-block, near the south end of Imagine Children’s Museum.

Rucker

The contractor continued work on the storm drain and on the waterline.

UPCOMING

Hoyt

Paving will continue...

Read on...

Rucker Renewal Project Updates
Posted on: July 22, 2019

Rucker Renewal project update 8-2-19

Rucker project logo

THIS WEEK

Hoyt

The contractor completed work on roadway demolition and began concrete paving and work to establish a crosswalk mid-block, near the south end of Imagine Children’s Museum. 

Rucker

The contractor began work on the storm drain, completed...

Read on...

Rucker Renewal Project Updates
Posted on: July 22, 2019

Rucker Renewal project update 7-26-19

Rucker project logo

THIS WEEK

Hoyt

The contractor completed work on storm drains, temporary lighting, irrigation, electrical conduit and road demolition except at the Hoyt/Pacific intersection. 

Rucker

Work on the waterline continued. Everett Avenue opened up following ...

Read on...

Rucker Renewal Project Updates
Posted on: July 22, 2019

Rucker Renewal project update 7-22-19

Rucker project logo

LAST WEEK

The contractor completed the bulk of the mobilization for the project.

Hoyt

  • Other completed tasks on Hoyt include erosion control, sawcutting, catch basin installation and roadway demolition.
  • During excavation on Hoyt, railroad ties and spikes were ...
Read on...

Rucker Renewal Project Updates
Posted on: July 12, 2019

Rucker Renewal project update

Rucker project logo

THIS WEEK

Big construction began! Jensen Construction began mobilizing on Mon., July 8, closing two blocks of Rucker between Everett and Hewitt, one block of Hoyt between Wall and Pacific, and a half a block of California west of Rucker. Detours are in pla...

Read on...

Rucker Renewal Project Updates
Posted on: July 1, 2019

Rucker Renewal project update

1914 Sanborn historic map

Phase 1 of the work to transform Rucker Avenue, between Everett and Hewitt Avenues, and a half a block of California is about to get underway. Construction is expected to begin July 8.

What to expect

  • The contractor will begin work on the two block section o...
Read on...

Rucker Renewal Project Updates